Clever Manufacturing Plus enables you to create "Engineering Change Requests" for the following types of information, directly within Business Central. 

  • Items
  • Stockkeeping Units
  • Production BOMs
  • Routings
  • Released Production Orders
  • Production By-Products

An "Engineering Change Request" cannot be created manually by the user. To create a new request, simply navigate to the relevant record within Business Central and select the Create Change Request option from the Engineering Changes menu, an example of which is shown below. 

Also available from the menu is the ability view existing "Engineering Change Requests" and "Engineering Change Orders" for the selected record.

Note: If creating a request for an Item, that does not currently have a Bill of Materials, Routing or By-Products defined, the request will be created without any Line details specified. 

When the "Engineering Change Request" is created, the following information will be populated automatically:

No. Populated using the Engineering Change Request Nos. specified in the "Manufacturing Setup" screen
Source Type

This is set based on record from which the request is created, as follows

  • Item - if created from an Item
  • Stockkeeping Unit - if created from a Stockkeeping Unit
  • Production BOM - if created from the Production BOM (or Production BOM Version)
  • Routing - if created from the Routing (or Routing Version)
  • Production By-Product - if created from the Production By-Product (or Production By-Product Version)
  • Production Order - if created from the a Released Production Order
Source No. Set to the key value of the related Master Data record, such as the No. from the Item record or No. from the Production BOM record
Description As above, this is copied from the related master data record
Status

When created, the Status is set to Open.

During the process of managing an "Engineering Change Request" the following Status' are possible.

  • Open - initial value upon creation and allows updates to the information within the Change Request
  • Pending Approval - this is the Status when the user has submitted a change for Approval and the information within the request cannot be changed 
  • Released - when Released the information cannot be changed and the change request can be implemented using the Register menu option. To make changes the request must be set to Open using the Reopen menu option
Created By This shows the user that has created the "Engineering Change Request"
Created Date The date at the time of creating the "Engineering Change Request"

To enable categorisation and reporting of changes that the business has identified when managing the manufacturing facility, you should first select the Reason Code within the General FastTab before then defining the full details of the changes that you wish to make. 

In addition the Reason Code, the following information can be set on the General FastTab, depending on the reason for the changes being required and also the configuration you have set in "Manufacturing Setup".

Effective Date This specifies the date from which the changes will begin which in turn will be used as the Starting Date on any Production BOM Version, Routing Version, or By-Product Version records that are created when the change request is registered
Routing Type If the change request will perform changes to a Routing then you are able to specify whether the routing will be Serial or Parallel. If the Source Type is a Routing then the Routing Type will be set the value from the Routing.
New Production BOM Version Code Only shown if the change could be used to create a new Production BOM Version and where the "Manufacturing Setup" Production BOM Version Nos. attribute is set to Manual Entry
New Routing Version Code Only shown if the change could be used to create a new Production Routing Version and where the "Manufacturing Setup" Routing Version Nos. attribute is set to Manual Entry
New Production By-Product Version Code Only shown if the change could be used to create a new Production By-Product Version and where the "Manufacturing Setup" Production By-Products Version Nos. attribute is set to Manual Entry

Depending on the Source Type of the "Engineering Change Request" the system will automatically populate the Lines section of the "Engineering Change Request" with manufacturing details related to the source record and you are then able to manage the changes as detailed here.

The creation of Lines is summarised below.

Source Type BOM Components Operations By-Products
Item Yes (if BOM linked) Yes (if Routing linked) Yes (if By-Products linked)
Stockkeeping Unit Yes (if BOM linked) Yes (if Routing linked) Yes (if By-Products linked)
Production BOM Yes
Routing Yes
Production By-Product Yes
Production Order Yes Yes Yes

Once the "Engineering Change Request" has been created you are then able to manage the information on the change request to specify the changes that you want to implement in relation to the manufacturing process, as identified here.